Works completed at the historic Awe Viaduct

Story Contracting on behalf of Network Rail and Scotland’s Railway are thrilled to announce the completion of the historic three – span wrought iron bridge, built in 1879, which carries the Crainlarich – Oban line over the River Awe, south of Taynuilt.

The scope of the work included:

  • Installation of a fully encapsulated access scaffold
  • Grit blasting and preparation of all associated steelwork
  • Condition-led repairs of steelwork
  • Masonry repairs to the structure’s piers and abutments
  • Timber deck replacement
  • Painting of steelwork

The project was completed over 34 weeks, ensuring the bridge’s longevity and enhancing its visual appeal in this much-loved part of the world.