Network Rail Infrastructure Projects (Civils)
£1m
3 months
Carlisle
64T of permanent interlocking sheet piles were installed surrounding each pier. The piles were driven to refusal, toeing into the mudstone bedrock. Following this, 282M3 concrete was poured between the pier and the sheet piles, with a capping beam formed at cut-off level.
The key challenge for the project was installing a temporary causeway in order to gain sufficient access across the river, and to undertake the works.
Stone filled gabion baskets were stacked upon the river bed, and 6m steel bridge plates used to span the gap. A stone piling platform was then installed between the piers, with large diameter pipes passing through the construction to maintain river flow.
The works were planned and implemented in controlled phases. This ensured sufficient cross-sectional flow of the river was maintained and allowed fish migration to be unhindered.
Our project team worked in close collaboration with the Environment Agency. Consent restrictions were agreed allowing the project to complete successfully within the permitted time window. This ensured the works had no adverse effect on the fish spawning season.
The site team successfully managed pedestrians passing through the site avoiding any need for closure or diversions to a world heritage trail, ‘Hadrian’s Wall’ footpath.
The River Eden encountered substantial flooding in December 2015 following works completion in October 2015. Inspections to the structure in January 2016 revealed no adverse effect to any of the bridge strengthening works, which carries the West Coast Mainline north of Carlisle into Scotland.
“Fantastic job done in extremely difficult conditions. Well done to you and your team!!” Jim Gabbat, Network Rail
“Looks good, well done to all involved.” Keith Sanderson, Network Rail
“Excellent job well done.” Peter Shrader, Network Rail
Find out how we can help you
To find out more about how we can help you deliver your project contact Paul Marrs on on 01228 590444.