Network Rail
Circa £500k
Bombo Burn
The scope of the works involved:
- Site Mobilisation & Establishment Works
- Installation of & Removal of Temporary Damming System
- Excavation & Profiling of Riverbed
- Installation of Reinforced Concrete Invert
- Installation of Rip Rap
- De-vegetation of Structure & Masonry repairs
- Demobilisation & Reinstatement Works
The project was able to celebrate success
and demonstrated best practice within the
following areas:
- Completion of works within programme, budget
and with no accidents or incidents within a
logistically challenging location. - The use of an effective over pumping damming
solution to maximise productivity whilst
maintaining a robust method of safe working
around the structure with no disruption to rail
traffic.
- The revision of design levels to mitigate any risk
which may be present of implementing works given
the shallow foundations present supporting the
structure. - The creation of a complete dry working area for an
effective and prolonged period to allow concrete
works to take place. - The success of delivering the project whilst adapting
to working within the Covid 19 pandemic. - The safe and efficient delivery of the whole works
package during challenging weather and water level
conditions.
Our project team worked in close collaboration with NWR,
environmental agencies and designers to ensure various
specialist works could be completed within the allocated time
frame for working within the watercourse, with solutions
such as an effective temporary damming system & ensuring
the works did not jeopardise the shallow foundations present
supporting the structure.
Our project team also effectively planned works and used an
innovative technology to enable the works to be planned and
implemented successfully in ever changing weather and water
level conditions
Circa 200t
Rip Rap installed
Circa 90 m3
concrete poured